Marking a Maintenance Event as Completed Late
Go to the Maintenance Grid page to see how to get here.
The Inspection Date has to have occurred after the Scheduled Date to be completed late.
Youβre on the Maintenance Grid.
The Maintenance Event has already been created.
Find the relevant asset from the list.
Find the Maintenance Event on the Maintenance Grid.
Click on the Maintenance Block.
The editor will open.
Click Inspection Date.
The calendar will open.
Select the date of the Maintenance Event.
Fill out the required fields regarding the delay.
Click Save.
The Maintenance Event has been marked as βCompletedβ. The Maintenance block will turn green with a red corner cut to indicate that the event was completed late.
If the late event is scheduled, you will be asked if you want to change all future events in line with the late inspection date.
This And All Future Events: will change the scheduled date of this event, and all future events.
Only This Event: will change the scheduled date of this event
Just Mark It Complete: will not change the schedule, and will mark the event complete but late.
Cancel: will not save any changes.
Preserving the original schedule
We recommend you preserve the original schedule by selecting Just Mark It Complete.